BP124365 - 2219 Belwood Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP124365 - 2219 Belwood Road | |
|---|---|
| Neighbourhood: | Westwood | 
| Street Address: | 2219 Belwood Road | 
| Type of Application: | Single / Two Family Alteration | 
| File Number: | BP124365 | 
| Date Application Submitted: | April 25, 2018 | 
| Application Description: | For the construction of a rear deck addition, work already completed, double permit fees. | 
| Application Status: | COMPLETED | 
| Permit Value: | $14,727.92 | 
| Builder: | BOEHM CONSTRUCTION LTD | 
| Issued Date: | July 13, 2018 | 
| File Close Date: | August 01, 2018 | 
| Expiry Date: | July 13, 2020 | 
Associated Properties
| Address | Zone | More | 
|---|---|---|
| 2219 BELWOOD ROAD | R5 | Property Report | 
Process Steps
| Task | Status | 
|---|---|
| 
                                FOOTING/FORMS
                                     Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.  | 
                            CANCELLED | 
| 
                                FOOTING/FORMS
                                     Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.  | 
                            PASSED | 
| 
                                PAPER/FLASHING/WATERPROOFING
                                     When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.  | 
                            CANCELLED | 
| 
                                FRAMING
                                     Rough in plumbing & electrical must be complete.  | 
                            CANCELLED | 
| 
                                FRAMING
                                     Rough in plumbing & electrical must be complete.  | 
                            FAILED | 
| 
                                FRAMING
                                     Rough in plumbing & electrical must be complete.  | 
                            PASSED | 
| 
                                FINAL-OLD
                                     Final approval as per requirements on plans.  | 
                            CANCELLED | 
| 
                                FINAL-OLD
                                     Final approval as per requirements on plans.  | 
                            FAILED | 
| 
                                FINAL-OLD
                                     Final approval as per requirements on plans.  | 
                            
                                PASSED
                                     2018-08-01  | 
                        
| Map | 
|---|
                          View in Google Earth (KML)
                     | 
                
            
            Disclaimer:
            
            The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
            Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
            The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
            
            The Information Provided within this website is for Informational Purposes Only.
            It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.
            
        

 View in Google Earth (KML)