BP123991 - 617 Hillcrest Ave
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP123991 - 617 Hillcrest Ave | |
---|---|
Neighbourhood: | Harewood |
Street Address: | 617 Hillcrest Ave |
Type of Application: | Single / Two Family Alteration |
File Number: | BP123991 |
Date Application Submitted: | December 28, 2017 |
Application Description: |
Rough in washroom, Relocate HW tank and laundry hook ups, add interior walls to create 2 Bedrooms. Revision - Feb 15/2019 : add strip footing, change existing garage to workshop/storage space. REVISION: 2022-JAN-18 Moved bathroom, added res-bar layout change |
Application Status: | COMPLETED |
Permit Value: | $3,900.00 |
Issued Date: | February 20, 2018 |
File Close Date: | August 03, 2022 |
Expiry Date: | February 20, 2022 |
Associated Properties
Address | Zone | More |
---|---|---|
617 HILLCREST AVENUE | R1 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PARTIAL |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
COMPLETED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
SCHEDULED |
FINAL
Final approval as per requirements on plans. |
PASSED
2022-08-03 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.