Application Description: |
Legal Secondary Suite, add washer to upper floor kitchen, deconstruction of a portion of basement that was illegally turned into living space and return back to the original carport. REVISION: Nov 20/17 - Carport conversion to unconditioned space. REVISION: Dec 15 2017 - change upstairs and downstairs laundry location REVISION: 2018-JAN-29- Delete three windows from storage room. Install two NAFS compliant doors, one to suite, and one to storage room....MLB |
Application Status: | COMPLETED |
Permit Value: | $15,000.00 |
Building Area: |
60.10 M2 646.91 ft2 |
Builder: | SUPER DAVE SERVICES |
Issued Date: | October 31, 2017 |
File Close Date: | February 01, 2018 |
Expiry Date: | October 31, 2019 |
Associated Properties
Address | Zone | More |
---|---|---|
4033 DEPARTURE BAY ROAD | R1 | Property Report |
Process Steps
Task | Status |
---|---|
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
CANCELLED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
CANCELLED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
FAILED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
FAILED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2018-02-01 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.