BP123696 - 561 Cumberland Place
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP123696 - 561 Cumberland Place | |
---|---|
Neighbourhood: | Linley Valley |
Street Address: | 561 Cumberland Place |
Type of Application: | Single / Two Family Dwelling |
File Number: | BP123696 |
Date Application Submitted: | September 21, 2017 |
Application Description: |
New construction of a single family dwelling with secondary suite on crawlspace REVISION, 2018-MAY-01....Add concrete topping to floor assemblies including exterior deck surfaces. see new attached Engineered drawings for details....MLB |
Application Status: | COMPLETED |
Permit Value: | $544,837.22 |
Building Area: |
299.52 M2 3,224.00 ft2 |
Builder: | OCEANS EDGE CONTRACTING LTD |
Issued Date: | November 16, 2017 |
File Close Date: | November 13, 2018 |
Expiry Date: | November 16, 2019 |
Associated Properties
Address | Zone | More |
---|---|---|
561 CUMBERLAND PLACE | R5 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PARTIAL |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
CANCELLED |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PARTIAL |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PARTIAL |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PARTIAL |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PARTIAL |
STORM CONNECTION
Pipe and Connection must be visible for inspection |
FAILED |
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
FAILED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
CANCELLED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler System must be complete and operating as intended |
PASSED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
CANCELLED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2018-11-13 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.