BP123621 - 1105 Cedar Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP123621 - 1105 Cedar Road | |
---|---|
Neighbourhood: | Chase River |
Street Address: | 1105 Cedar Road |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP123621 |
Date Application Submitted: | August 24, 2017 |
Application Description: | Construction of a new slab on grade 27.8m2 scale house complete with accessible washroom. |
Application Status: | COMPLETED |
Permit Value: | $141,308.00 |
Builder: | ISLAND WEST COAST DEVELOPMENTS |
Issued Date: | September 27, 2017 |
File Close Date: | December 22, 2017 |
Associated Properties
Address | Zone | More |
---|---|---|
1105 CEDAR ROAD | CS2 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2017-12-22 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.