Date Application Submitted: | June 28, 2017 |
Application Description: |
Interior alterations to include new doors and two washrooms, one of which is accessible. Kitchen located in the basement must be removed under this permit. REVISION Sept 5 ...Crawlspace floor plan submitted, closet installed in place of stairs and sliding doors as indicated on drawings, sinks in exam rooms. REVISION Sept 19 - Added sink to crawlspace, changed shower to sink. |
Application Status: | COMPLETED |
Permit Value: | $3,000.00 |
Issued Date: | July 28, 2017 |
File Close Date: | January 29, 2020 |
Expiry Date: | July 28, 2019 |
Associated Properties
Address | Zone | More |
---|---|---|
210 MILTON STREET | DT10 | Property Report |
Process Steps
Task | Status |
---|---|
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2020-01-29 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.