BP123298 - 127 Bray Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP123298 - 127 Bray Road | |
|---|---|
| Neighbourhood: | Linley Valley | 
| Street Address: | 127 Bray Road | 
| Type of Application: | Single / Two Family Dwelling | 
| File Number: | BP123298 | 
| Date Application Submitted: | May 24, 2017 | 
| Application Description: | Three storey single family dwelling slab on grade with a secondary suite Jun 30/17: Revision -roof/beam layout changed, cantilevered roof added to rear deck Apr 5/18: Revision - 9' crawlspace changed to heated space | 
| Application Status: | COMPLETED | 
| Permit Value: | $600,000.00 | 
| Building Area: | 380.62 M2 4,096.96 ft2 | 
| Issued Date: | June 26, 2017 | 
| File Close Date: | April 10, 2018 | 
| Expiry Date: | June 26, 2019 | 
Associated Properties
| Address | Zone | More | 
|---|---|---|
| 127 BRAY ROAD | R10 | Property Report | 
Process Steps
| Task | Status | 
|---|---|
| FOOTING / FORMS Inspection of forms prior to any concrete being poured | PARTIAL | 
| FOOTING / FORMS Inspection of forms prior to any concrete being poured | PARTIAL | 
| FOOTING / FORMS Inspection of forms prior to any concrete being poured | PASSED | 
| PERIMETER DRAIN For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering | PARTIAL | 
| PERIMETER DRAIN For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering | PASSED | 
| UNDERSLAB PLUMBING Complete underslab plumbing must be visible | PASSED | 
| UNDERSLAB INSULATION Inspection required prior to placing slab concrete | PASSED | 
| STORM CONNECTION Pipe and Connection must be visible for inspection | FAILED | 
| STORM CONNECTION Pipe and Connection must be visible for inspection | PASSED | 
| SANITARY CONNECTION Pipe and Connection must be visible for inspection | FAILED | 
| SANITARY CONNECTION Pipe and Connection must be visible for inspection | PASSED | 
| WATER CONNECTION Pipe and Connection must be visable for inspection | FAILED | 
| WATER CONNECTION Pipe and Connection must be visable for inspection | CANCELLED | 
| WATER CONNECTION Pipe and Connection must be visable for inspection | PASSED | 
| ROUGH IN PLUMBING Rough in plumbing must be complete including potable water piping | PARTIAL | 
| ROUGH IN PLUMBING Rough in plumbing must be complete including potable water piping | PARTIAL | 
| ROUGH IN PLUMBING Rough in plumbing must be complete including potable water piping | PASSED | 
| LATERAL BRACING & SHEATHING All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. | FAILED | 
| LATERAL BRACING & SHEATHING All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. | PARTIAL | 
| LATERAL BRACING & SHEATHING All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. | PASSED | 
| PAPER/FLASHING/WATERPROOFING When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. | FAILED | 
| PAPER/FLASHING/WATERPROOFING When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. | PARTIAL | 
| PAPER/FLASHING/WATERPROOFING When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. | PASSED | 
| ROUGH IN SPRINKLER Rough in sprinkler must be complete and visable for inspection | PARTIAL | 
| FRAMING Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval | FAILED | 
| FRAMING Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval | FAILED | 
| FRAMING Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval | CANCELLED | 
| FRAMING Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval | CANCELLED | 
| FRAMING Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval | PASSED | 
| INSULATION Insulation and vapour barrier to be complete prior to inspection | FAILED | 
| INSULATION Insulation and vapour barrier to be complete prior to inspection | PASSED | 
| INTERIOR BRACED WALL PANELS The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. | CANCELLED | 
| INTERIOR BRACED WALL PANELS The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. | FAILED | 
| INTERIOR BRACED WALL PANELS The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. | PASSED | 
| SPRINKLER FINAL-OLD Sprinkler System must be complete and operating as intended | PARTIAL | 
| SPRINKLER FINAL-OLD Sprinkler System must be complete and operating as intended | PASSED | 
| OCCUPANCY-OLD Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish | FAILED | 
| OCCUPANCY-OLD Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish | PASSED 2018-04-10 | 
| Map | 
|---|
|  View in Google Earth (KML) | 
            
            Disclaimer:
            
            The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
            Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
            The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
            
            The Information Provided within this website is for Informational Purposes Only.
            It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.
            
        