BP123077 - 103 - 6461 Metral Drive

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP123077 - 103 - 6461 Metral Drive
Neighbourhood: Pleasant Valley    
Street Address: 103 - 6461 Metral Drive
Type of Application: Leasehold Improvements
File Number: BP123077
Date Application Submitted: March 24, 2017
Application Description: Tenant improvement (Oxygen Yoga & Fitness) A2 occupancy, including new interior walls, 2 accessible washrooms, showers. Area of 183.76m2 and an occupant load of 50 persons limited by available washrooms. 2 hr FS/FRR walls constructed under BP123142.

Building Classification: Building Area = 3260 m2, 2012 BCBC, Group E occupancy, 3.2.2.62, with a minor A2 (occupying 5% of the building floor area), single storey, any height, any area,non combustible construction, sprinklered with fire alarm system building. Floor assemblies, loadbearing walls and columns require 2hr FRR. Mezzanines require 1hr FRR.

REVISION: Jan.5/18 - Add mop sink and move HWT to studio area with a closet.

REVISION: Feb.14/18 - Revise architectural plans and all schedules to update CRP. Change sprinkler layout and add fire protection engineer.
Application Status: COMPLETED
Permit Value: $200,000.00
Issued Date: July 11, 2017
File Close Date: February 15, 2018
Expiry Date: July 11, 2019

Associated Properties

Address Zone More
6461 METRAL DRIVE CC4 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visible for inspection.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
FINAL-OLD

Final Approval as per requirements on plans.

FAILED
FINAL-OLD

Final Approval as per requirements on plans.

PASSED

2018-02-15

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy