BP122898 - 570 St George Street

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP122898 - 570 St George Street
Neighbourhood: Townsite    
Street Address: 570 St George Street
Type of Application: Locate Permit
File Number: BP122898
Date Application Submitted: February 08, 2017
Application Description: Relocate out of town residential building to city lot and create a carriage house accessory building on crawl space.

2018-JUN-13 REVISION: Add ground level deck.
Application Status: COMPLETED
Permit Value: $15,000.00
Building Area: 74.20 M2
798.68 ft2
Issued Date: April 11, 2017
File Close Date: June 21, 2018
Expiry Date: April 11, 2019

Associated Properties

Address Zone More
570 ST GEORGE STREET R1 Property Report

Process Steps

Task Status
EXCAVATION

Excavation of soil, prior to placing forms.

PASSED
FOOTING/FORMS

Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite.

CANCELLED
FOOTING/FORMS

Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite.

FAILED
FOOTING/FORMS

Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite.

PARTIAL
PERIMETER DRAIN

For Perimeter Drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For Perimeter Drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concete.

PARTIAL
STORM CONNECTION

Pipe connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe Connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe Connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

CANCELLED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

SCHEDULED
FRAMING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
FRAMING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
INSULATION

Rough in sprinkler must be complete and visible for inspection.

CANCELLED
INSULATION

Rough in sprinkler must be complete and visible for inspection.

PASSED
PAPER/FLASHING/WATERPROOFING

To take place after installation of framing, sheathing, building paper, flashing, and/or weatherproofing of openings and after window installation, but before installation of any siding product or stucco wire.

PASSED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy