BP122399 - 1724 Harvest Place
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP122399 - 1724 Harvest Place | |
---|---|
Neighbourhood: | Chase River |
Street Address: | 1724 Harvest Place |
Type of Application: | Accessory Building |
File Number: | BP122399 |
Date Application Submitted: | September 02, 2016 |
Application Description: |
Accessory Building art studio. Slab on grade Revision, 2017-JAN-25 Crawlspace with TJI instead of slab. Relocate entry door, Change roof assy, to 2X12 from Truss. 1X8 diag sheathing from OSB...MLB |
Application Status: | COMPLETED |
Building Area: |
43.50 M2 468.23 ft2 |
Builder: | BOEHM CONSTRUCTION LTD |
Issued Date: | October 21, 2016 |
File Close Date: | July 05, 2017 |
Expiry Date: | October 22, 2018 |
Associated Properties
Address | Zone | More |
---|---|---|
1724 HARVEST PLACE | R1 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
PARTIAL |
FOOTING/FORMS
Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2017-07-05 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.