BP122060 - 5200 Dublin Way, BLDG A - Units #100 & #101
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP122060 - 5200 Dublin Way, BLDG A - Units #100 & #101 | |
---|---|
Neighbourhood: | Pleasant Valley |
Street Address: | 5200 Dublin Way, BLDG A - Units #100 & #101 |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP122060 |
Date Application Submitted: | June 01, 2016 |
Application Description: |
Bldg A, Units #100 & #101 - Construction of a 431.3m2 building. 2 CRU's, accessible washrooms, unit #100 - 186.2m2 with 59m2 mezzanine over slab on grade, Unit #101 - 186.1m2 over crawlspace. Group D, 3.2.2.61 facing 1 street, 2 Storey, sprinklered, 1hr FRR between suites, service room separated with 1hr FRR in walls and floor. |
Application Status: | COMPLETED |
Permit Value: | $700,000.00 |
Builder: | WESTMARK CONSTRUCTION LTD |
Issued Date: | August 22, 2016 |
File Close Date: | July 26, 2017 |
Expiry Date: | August 22, 2018 |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
FAILED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
CANCELLED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD |
PASSED
2017-07-26 |
FINAL-OLD
Final approval as per requirements on plans. |
SCHEDULED |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.