BP121989 - 904 Pavan Place

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP121989 - 904 Pavan Place
Neighbourhood: Harewood    
Street Address: 904 Pavan Place
Type of Application: Single / Two Family Dwelling
File Number: BP121989
Date Application Submitted: May 13, 2016
Application Description: For construction of a two storey single family dwelling with suite, slab on grade construction.

REVISION: October 25/16 - Move BWP for electrical panel.

REVISION 2017-FEB-17,
-Change doors into workshop to double doors at 5ft wide.
-Delete Pocket door into water closet room at ensuite, and reduce wall height to 1/2 height wall i lieu.
-reduce wall to half height wall at suite entry door to counter height.
No BWP affected....MLB

REVISION: Mar 29, 2017 Storage room in workshop.

REVISION SEP 30, 2019: Add Structural for over height stone veneer.
Application Status: COMPLETED
Permit Value: $439,674.68
Building Area: 347.46 M2
3,740.02 ft2
Issued Date: June 27, 2016
File Close Date: October 10, 2019
Expiry Date: June 27, 2020

Associated Properties

Address Zone More
904 PAVAN PLACE R1 Property Report

Process Steps

Task Status
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PARTIAL
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PARTIAL
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PASSED
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PASSED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

CANCELLED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
STORM CONNECTION

Pipe and Connection must be visible for inspection

PARTIAL
STORM CONNECTION

Pipe and Connection must be visible for inspection

PASSED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

FAILED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PARTIAL
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PASSED
WATER CONNECTION

Pipe and Connection must be visable for inspection

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

PASSED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

FAILED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

FAILED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PASSED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

FAILED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

FAILED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PARTIAL
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PASSED
MONITORING FIELD REVIEW CANCELLED
OCCUPANCY-OLD

Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish

FAILED
OCCUPANCY-OLD

Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish

FAILED
OCCUPANCY-OLD

Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish

PASSED

2019-10-10

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy