BP121372 - 430 Milford Crescent
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP121372 - 430 Milford Crescent | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 430 Milford Crescent |
Type of Application: | Single / Two Family Alteration |
File Number: | BP121372 |
Date Application Submitted: | October 21, 2015 |
Application Description: |
Work to remove notice on title: Remove existing fireplace and chimney, install staircase from basement to main level, fire separate between attached garages, and construct a new deck over carport. Revision: Feb 18/17 - move location of closet walls in mstr bed, remove partition walls in basement, remove partition wall in mstr bed closet, remove partition wall between dining room & living room. mv REVISION: DECK AND BACK STAIRS REMOVED FROM PERMIT JULY 3, 2018 |
Application Status: | COMPLETED |
Permit Value: | $19,000.00 |
Issued Date: | November 24, 2015 |
File Close Date: | August 21, 2018 |
Expiry Date: | November 24, 2019 |
Associated Properties
Address | Zone | More |
---|---|---|
430 MILFORD CRESCENT | R15 | Property Report |
Process Steps
Task | Status |
---|---|
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
SCHEDULED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
COMPLETED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
COMPLETED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2018-08-21 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.