BP120818 - 100 Chapel Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP120818 - 100 Chapel Street | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 100 Chapel Street |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP120818 |
Date Application Submitted: | May 05, 2015 |
Application Description: |
St Pauls Anglican Church. Replacement of the existing Church Hall , meeting rooms and offices with New Addition and new elevator. Building Classification 3.2.2.26, 2 storey + mezzanine, combustible construction, sprinklered and fire alarm throughout. New Building area for code purposes 717 sm. 1st storey 474 sm, 2nd storey 716.5 sm, mezzanine 155.7 sm. Total gross floor area = 1346.2 sm Occupant load 236 fixed seats, existing church. Occupant load for hall = 174 persons, Total Building Occupant load = 410 persons. 4 exits , New universal toilet room, new accessible female and male washroom . Minor Renovation to the existing church including changes in the narthex, removing stairs to the lower floor and mezzanine , new enclosed nursery in the church nave , new access to mezzanine through a new exit stairwell. Sprinklers throughout. |
Application Status: | COMPLETED |
Permit Value: | $2,400,000.00 |
Builder: | HEATHERBRAE BUILDERS CO LTD |
Issued Date: | June 12, 2015 |
File Close Date: | December 04, 2017 |
Expiry Date: | June 12, 2017 |
Associated Properties
Address | Zone | More |
---|---|---|
100 CHAPEL STREET | DT5 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2017-12-04 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.