BP120296 - 130 Giggleswick Place
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP120296 - 130 Giggleswick Place | |
---|---|
Neighbourhood: | Townsite |
Street Address: | 130 Giggleswick Place |
Type of Application: | Single / Two Family Alteration |
File Number: | BP120296 |
Date Application Submitted: | November 06, 2014 |
Application Description: |
For the construction of a Secondary Suite to be constructed in basement of existing SFD. Revision: Jan 22, 2015 -- Re locate furnace and HWT to exterior room, add W/D to bottom of stairs for main dwelling. |
Application Status: | COMPLETED |
Permit Value: | $20,000.00 |
Builder: | TECTONICA MANAGEMENT INC |
Issued Date: | December 08, 2014 |
File Close Date: | February 01, 2018 |
Expiry Date: | December 08, 2018 |
Associated Properties
Address | Zone | More |
---|---|---|
130 GIGGLESWICK PLACE | R5 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PARTIAL |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
PARTIAL |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
COMPLETED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2018-02-01 |
FINAL-OLD
Final approval as per requirements on plans. |
SCHEDULED |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.