BP120276 - 2150 Departure Bay Road - Drawings Scanned & Attached
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP120276 - 2150 Departure Bay Road - Drawings Scanned & Attached | |
---|---|
Neighbourhood: | Departure Bay |
Street Address: | 2150 Departure Bay Road - Drawings Scanned & Attached |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP120276 |
Date Application Submitted: | October 28, 2014 |
Application Description: |
Relocation of an existing daycare into a portion of the lower floor of the Church including renovation to existing storage and activity rooms. No change in occupancy classification or use. Existing ceiling finish within the renovation area will be replaced with 5/8" Type X drywall and new walls will be constructed to provide a 45 minute fire separations. Daycare 2300 ft2, 36 children in care and 4 staff. Existing daycare, 40 children in care and 4 staff. Scope of work includes two, two fixture W/Cs and double sink and dishwasher. |
Application Status: | COMPLETED |
Permit Value: | $50,000.00 |
Builder: | MAXX CONTRACTING & LANDSCAPING |
Issued Date: | January 02, 2015 |
File Close Date: | March 30, 2015 |
Expiry Date: | January 02, 2017 |
Associated Properties
Address | Zone | More |
---|---|---|
2150 DEPARTURE BAY ROAD | CS1 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
FAILED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2015-03-30 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.