BP120016 - 3405, 3411 & 3417 Ocean Mist Place
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP120016 - 3405, 3411 & 3417 Ocean Mist Place | |
---|---|
Neighbourhood: | Linley Valley |
Street Address: | 3405, 3411 & 3417 Ocean Mist Place |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP120016 |
Date Application Submitted: | July 25, 2014 |
Application Description: |
Construction of 3-Plex, Block D (3405, 3411 & 3417 Ocean Mist Place) 340.9 m2, 2 storey, C occupancy designed to Part 9, sprinklered, 1 hour fire separation required beween dwelling units. Gross Building Floor Area 520.1 m2. |
Application Status: | COMPLETED |
Permit Value: | $900,000.00 |
Builder: | HAZELWOOD HOLDINGS LTD |
Issued Date: | November 13, 2014 |
File Close Date: | April 15, 2016 |
Expiry Date: | November 13, 2016 |
Associated Properties
Address | Zone | More |
---|---|---|
3405 OCEAN MIST PLACE | R6 | Property Report |
3417 OCEAN MIST PLACE | R6 | Property Report |
3411 OCEAN MIST PLACE | R6 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
CANCELLED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
SCHEDULED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD |
PASSED
2016-04-15 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.