Application Description: |
Renovations of top floor within attic trusses. Upgrade existing secondary suite to authorized. Revision, 2015-MAR-26, relocated 3 window units, moved two closets, and added pony wall at stairwell opening. Adding stackable W/D in upstairs bathroom former linen closet. Change Cedar shake with rainscreen in gable ends to vinyl shakes, no rainscreen required.....MLB |
Application Status: | COMPLETED |
Permit Value: | $80,000.00 |
Building Area: |
83.61 M2 899.97 ft2 |
Builder: | A T C HOME SOLUTIONS INC |
Issued Date: | December 08, 2014 |
File Close Date: | October 06, 2016 |
Expiry Date: | December 08, 2016 |
Associated Properties
Address | Zone | More |
---|---|---|
95 MILTON STREET | R14 | Property Report |
Process Steps
Task | Status |
---|---|
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
FAILED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
COMPLETED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2016-10-06 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.