BP119968 - 1820 Summerhill Place (Foundation) Drawings Attached
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP119968 - 1820 Summerhill Place (Foundation) Drawings Attached | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 1820 Summerhill Place (Foundation) Drawings Attached |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP119968 |
Date Application Submitted: | June 23, 2014 |
Application Description: |
Summerhill Residential Apartment - FOUNDATION PERMIT ONLY - BUILDING DESCRIPTION: 103 Residential units - 4 storeys , Group C, 3.2.2.50, x-reference BP119896 for the building permit for 4 storey - GFA - 7905.86 m2 103 rental units. No construction beyond the foundation stage until BP119896 is issued. |
Application Status: | COMPLETED |
Permit Value: | $1,417,400.20 |
Builder: | THE MOLNAR GROUP |
Issued Date: | July 21, 2014 |
File Close Date: | December 22, 2015 |
Expiry Date: | July 21, 2016 |
Associated Properties
Address | Zone | More |
---|---|---|
1820 SUMMERHILL PLACE | R8 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2015-12-22 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.