BP119931 - 3379 Stephenson Point Road / 3420 Budehaven
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP119931 - 3379 Stephenson Point Road / 3420 Budehaven | |
---|---|
Neighbourhood: | Hammond Bay |
Street Address: | 3379 Stephenson Point Road / 3420 Budehaven |
Type of Application: | Single / Two Family Dwelling |
File Number: | BP119931 |
Date Application Submitted: | July 03, 2014 |
Application Description: |
For construction of a 2 storey side by side duplex with one attached garage and one detached garage. Lot coverage is 39.14%, maximum permitted is 40.0%. Inspections for detached garage are under BP119936 Aug 29/14 - The following was missed in the permit conditions (5% reduction was applied): Geotechnical field review for bearing capacity of the soil, compaction of engineered fill, and permanent dewatering by Chris Hudec, P. Eng. of Lewkowich Engineering Associates Ltd. (Schedule B). mv |
Application Status: | COMPLETED |
Permit Value: | $458,241.82 |
Building Area: |
394.56 M2 4,247.00 ft2 |
Builder: | WINDLEY CONTRACTING LTD |
Issued Date: | August 13, 2014 |
File Close Date: | July 29, 2015 |
Expiry Date: | August 13, 2016 |
Associated Properties
Address | Zone | More |
---|---|---|
3420 BUDEHAVEN DRIVE | R1 | Property Report |
3379 STEPHENSON POINT ROAD | R1 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PARTIAL |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
FAILED |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PARTIAL |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
FAILED |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PASSED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2015-07-29 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.