| Type of Application: | Commercial / Multi / Industrial | 
| File Number: | BP119053 | 
| Date Application Submitted: | December 18, 2014 | 
| Application Description: | PH 8 - MULTI- FAMILY DEVELOPMENT DESCRIPTION 65 units in 22 buildings - 15 duplex and 7 - 5 unit townhouses This permit is for 1 - 5 unit townhouse - Building 1 -(Type A) 2 storey on slab, with 1 hour fire separation between each unit, sprinklered Phase 8 BUILDING 1- under this permit. 141, 143, 145, 147, 149 - 1720 Dufferin - 472.13m2 GFA, 5 unit townhouse. revised Revised Jan. 12, 2016 washroom to each unit. JB | 
| Application Status: | COMPLETED | 
| Permit Value: | $478,160.44 | 
| Builder: | GABLECRAFT WESTHILL LP | 
| Issued Date: | September 15, 2015 | 
| File Close Date: | April 26, 2016 | 
| Expiry Date: | September 15, 2017 | 
Associated Properties
| Address | Zone | More | 
|---|---|---|
| 149 1720 DUFFERIN CRESCENT | R8 | Property Report | 
| 147 1720 DUFFERIN CRESCENT | R8 | Property Report | 
| 145 1720 DUFFERIN CRESCENT | R8 | Property Report | 
| 143 1720 DUFFERIN CRESCENT | R8 | Property Report | 
| 141 1720 DUFFERIN CRESCENT | R8 | Property Report | 
Process Steps
| Task | Status | 
|---|---|
| FOOTING/FORMS Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. | PASSED | 
| PERIMETER DRAIN For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. | CANCELLED | 
| PERIMETER DRAIN For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. | PASSED | 
| UNDERSLAB PLUMBING complete underslab plumbing must be visible. | PARTIAL | 
| UNDERSLAB PLUMBING complete underslab plumbing must be visible. | PASSED | 
| UNDERSLAB INSULATION Inspection required prior to placing slab concrete. | PASSED | 
| STORM CONNECTION Pipe and connection must be visible for inspection. | PASSED | 
| SANITARY CONNECTION Pipe and connection must be visible for inspection. | PASSED | 
| WATER CONNECTION Pipe and connection must be visible for inspection. | PASSED | 
| ROUGH IN PLUMBING Rough in plumbing must be complete including potable water piping. | PASSED | 
| PAPER/FLASHING/WATERPROOFING When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. | PARTIAL | 
| PAPER/FLASHING/WATERPROOFING When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. | PASSED | 
| ROUGH IN SPRINKLER Rough in sprinkler must be complete and visable for inspection. | PASSED | 
| FRAMING Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. | PARTIAL | 
| FRAMING Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. | PARTIAL | 
| FRAMING Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. | PASSED | 
| INSULATION Insulation and vapour barrier to be complete prior to inspection. | PARTIAL | 
| INSULATION Insulation and vapour barrier to be complete prior to inspection. | PASSED | 
| INTERIOR BRACED WALL PANELS The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. | PARTIAL | 
| INTERIOR BRACED WALL PANELS The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. | PARTIAL | 
| INTERIOR BRACED WALL PANELS The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. | PASSED | 
| SPRINKLER FINAL-OLD Sprinkler system must be complete and operating as intended. | PASSED | 
| OCCUPANCY-OLD | FAILED | 
| OCCUPANCY-OLD | PASSED 2016-04-26 | 
| Map | 
|---|
|  View in Google Earth (KML) | 
            
            Disclaimer:
            
            The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
            Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
            The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
            
            The Information Provided within this website is for Informational Purposes Only.
            It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.
            
        