BP118719 - 95 Tenth - SCANNED
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP118719 - 95 Tenth - SCANNED | |
---|---|
Neighbourhood: | Harewood |
Street Address: | 95 Tenth - SCANNED |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP118719 |
Date Application Submitted: | June 27, 2013 |
Application Description: | Chinook Scaffold Systems - Addition of 49m2 to second floor, board room and office space. Existing Part9 F2/D Second storey travel distance maximum 25m single exit permitted. Combustible construction permitted. Interconnected floor space permitted. FRR of columns and supporting walls 45min. 45min Fire Separation for exits. Floors are required to be constructed as 45min FS (Interconnected floor space permitted.) Sink added to new staff room. |
Application Status: | COMPLETED |
Permit Value: | $90,000.00 |
Issued Date: | July 18, 2013 |
File Close Date: | October 17, 2013 |
Associated Properties
Address | Zone | More |
---|---|---|
95 TENTH STREET | COR3 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2013-10-17 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.