BP118605 - 5694 Ocean View Terrace
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP118605 - 5694 Ocean View Terrace | |
---|---|
Neighbourhood: | North Slope |
Street Address: | 5694 Ocean View Terrace |
Type of Application: | Single / Two Family Dwelling |
File Number: | BP118605 |
Date Application Submitted: | May 14, 2013 |
Application Description: |
Construction of a two storey single family dwelling with 2 bay garage equipped with through doors, and two bedroom secondary suite on slab on grade and crawlspace. Revision 1: Dec 24, 2013-- Move closet in suite bedroom and add 4ox4o window. Move location of suite entrance from under stairs to off living room. Revision 2:Jan 14, 2014-- Revision: Close in area below deck to be unheated storage. No venting req'd. Revision 3: Mar 6, 2014-- Change location of braced wall panel in kitchen, two closets made in suite, on in living room and a second in suite bedroom and front door size changed to 69". Revision 4: Mar 21, 2014-- Closet eliminated from entry foyer, closet added to hallway, laundry room and under stairs. BWP eliminated at hallway near den and 2- 36"BWP's added to hall closet. |
Application Status: | COMPLETED |
Permit Value: | $371,436.90 |
Building Area: |
350.31 M2 3,770.70 ft2 |
Builder: | DEEP ROOT DEVELOPMENTS LTD |
Issued Date: | July 16, 2013 |
File Close Date: | July 14, 2014 |
Expiry Date: | July 16, 2015 |
Associated Properties
Address | Zone | More |
---|---|---|
5694 OCEANVIEW TERRACE | R5 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
PASSED |
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PARTIAL |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PARTIAL |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PARTIAL |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2014-07-14 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.