BP117689 - 190 Harewood
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP117689 - 190 Harewood | |
---|---|
Neighbourhood: | University District |
Street Address: | 190 Harewood |
Type of Application: | Single / Two Family Alteration |
File Number: | BP117689 |
Date Application Submitted: | August 14, 2012 |
Application Description: | Construct deck and stairs |
Application Status: | COMPLETED |
Permit Value: | $2,200.00 |
Building Area: |
2.97 M2 31.97 ft2 |
Builder: | BERT BALES CARPENTRY |
Issued Date: | August 24, 2012 |
File Close Date: | September 12, 2013 |
Associated Properties
Address | Zone | More |
---|---|---|
190 HAREWOOD ROAD | R5 | Property Report |
Process Steps
Task | Status |
---|---|
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
SCHEDULED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
FAILED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2013-09-12 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.