BP117440 - 3638 Overlook Drive
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP117440 - 3638 Overlook Drive | |
---|---|
Neighbourhood: | Hammond Bay |
Street Address: | 3638 Overlook Drive |
Type of Application: | Single / Two Family Alteration |
File Number: | BP117440 |
Date Application Submitted: | June 04, 2012 |
Application Description: |
Construct a two storey addition to an existing single family dwelling including a secondary suite with slab on grade. Revision: Change shape/layout of upstairs 3 piece bathroom. Frame in boot room off front entry way with new footings, foundation and slab-on-grade. Neither revision effects setbacks.JB Revision Sept 10, 2012, Move Upper Living Room window, Change windows over deck to 6-0 X 5-0, Change Suite Living Room to 6-0 X5-0....MLB Revision: Aug 29, 2013-- Basement layout to be confirmed at final insepction. Revision October 28, 2013 Delete tub from upstairs ensuite and add shower...MLB |
Application Status: | COMPLETED |
Permit Value: | $158,757.67 |
Building Area: |
347.53 M2 3,740.78 ft2 |
Issued Date: | June 06, 2012 |
File Close Date: | November 04, 2013 |
Associated Properties
Address | Zone | More |
---|---|---|
3638 OVERLOOK DRIVE | R1 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
FAILED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2013-11-04 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.