BP117382 - 2400 Labieux (Parent) Ph 3- -- Scanned
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP117382 - 2400 Labieux (Parent) Ph 3- -- Scanned | |
---|---|
Neighbourhood: | Diver Lake |
Street Address: | 2400 Labieux (Parent) Ph 3- -- Scanned |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP117382 |
Date Application Submitted: | May 16, 2012 |
Application Description: |
2400 Labieux Road (Parent) - Sprinklered, 29 multi-family unit development Phase 3 BP117382 - Duplex A - 2410, 2412 Parveen Place; INSPECTIONS under BP117382 See BP117381 for Building Permit Information |
Application Status: | COMPLETED |
Builder: | OM DEVELOPMENT INC |
Issued Date: | June 05, 2012 |
File Close Date: | November 06, 2012 |
Associated Properties
Address | Zone | More |
---|---|---|
2412 PARVEEN PLACE | R6 | Property Report |
2410 PARVEEN PLACE | R6 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
FAILED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
FAILED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD |
PASSED
2012-10-29 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.