Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP117255 |
Date Application Submitted: | April 13, 2012 |
Application Description: |
Interior and exterior renovation for new Target store in existing retail space (Zellers). Nanaimo North Town Centre - Existing Group E building 3.2.2.57, noncombustible construction sprinklered with fire alarm. Mezzanines require a 1 hour fire rating. Design build option taken for sprinkler renovation. |
Application Status: | COMPLETED |
Permit Value: | $6,750,000.00 |
Builder: | P C L CONSTRUCTORS WESTCOAST INC |
Issued Date: | November 08, 2012 |
File Close Date: | April 26, 2013 |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
SCHEDULED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
FINAL-OLD
Final approval as per requirements on plans. |
PARTIAL |
FINAL-OLD
Final approval as per requirements on plans. |
PARTIAL |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2013-04-26 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.