BP117172 - 2300 Bowen Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP117172 - 2300 Bowen Road | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 2300 Bowen Road |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP117172 |
Date Application Submitted: | March 26, 2012 |
Application Description: |
Cliff McNabb Arena - 27.71 m2 addition to the existing building. Addition will house the Zamboni and a melt pit. Modifications to the refrigeration system and sprinkler changes in refrigeration room for new rated ceiling. New roof, replacing exterior siding, perimeter repairs. New heating/exhaust /venting systems. 1.5 hour FRR/FS provided around Zamboni, 1 hour FRR/FS around the refrigeration room, new eyewash/shower, relocation of the storm drain and new sanitary drain connected to existing system. 3.2.2.33 - Existing Group A-3 Sprinklered, non-combustible or combustible building. |
Application Status: | COMPLETED |
Permit Value: | $1,600,000.00 |
Issued Date: | April 20, 2012 |
File Close Date: | August 26, 2015 |
Expiry Date: | April 20, 2014 |
Associated Properties
Address | Zone | More |
---|---|---|
2300 BOWEN ROAD | PRC1 , PRC3 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
PARTIAL |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2015-08-26 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.