BP116099 - 2400 Labieux (Parent) Ph 2 - 2401, 2403 Brandon Way (Duplex A) -- Scanned
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP116099 - 2400 Labieux (Parent) Ph 2 - 2401, 2403 Brandon Way (Duplex A) -- Scanned | |
|---|---|
| Neighbourhood: | Diver Lake |
| Street Address: | 2400 Labieux (Parent) Ph 2 - 2401, 2403 Brandon Way (Duplex A) -- Scanned |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP116099 |
| Date Application Submitted: | October 26, 2010 |
| Application Description: |
2400 Labieux Road (Parent) - Sprinklered, 29 multi-family unit development 13 duplexes, 1 triplex. Phase 2 includes 3 duplexes. 6 units @ 1260 sq.ft. (702.35 m2) 2401/2403 Brandon Way- Type A ~ INSPECTIONS ONLY (BP116099) 2405/2407 Brandon Way - Type A ~ INSPECTIONS ONLY (BP116100) 2409/2411 Brandon Way - Type A ~ INSPECTIONS ONLY (BP116101) See BP115699 for Building Permit Information |
| Application Status: | COMPLETED |
| Permit Value: | $900,000.00 |
| Builder: | OM DEVELOPMENT INC |
| Issued Date: | April 15, 2011 |
| File Close Date: | February 23, 2012 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 2401 BRANDON WAY | R6 | Property Report |
| 2403 BRANDON WAY | R6 | Property Report |
| 2400 LABIEUX ROAD | R6 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
| OCCUPANCY-OLD |
PASSED
2012-02-23 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)