BP115784 - 6300 Hammond Bay Road (Alias -6400 Applecross Rd)(New Transit Bldg)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP115784 - 6300 Hammond Bay Road (Alias -6400 Applecross Rd)(New Transit Bldg)
Neighbourhood: Dover    
Street Address: 6300 Hammond Bay Road (Alias -6400 Applecross Rd)(New Transit Bldg)
Type of Application: Commercial / Multi / Industrial
File Number: BP115784
Date Application Submitted: November 30, 2010
Application Description: Transit building - 552.45 m2 GFA addition consisting of new paint bay with storage areas (with new 49.47 m2 second floor above storage area), bus wash, service bay & fuel island with canopy.

Separate permit required for signs.

Transit Bldg. Part 3, 2 storey, sprinklered, fire alarm, accessible, Group D & F-2 repair garage, BCBC area 1037.9 m2, building classification 3.2.2.72., combustible construction, 45min FRR/FS floor assemblies and 45 FRR for loadbearing supports. 2 hr FS between repair garage and office areas.

Oct 31/11 -Geotech (Darren Clark of Lewkowich Engineering) added to project
Dec. 6/11 - Mechanical (high pressure gas piping &equipment only) (M.A. Epp of Jenmar Compressors Inc.) added to project.
Application Status: COMPLETED
Permit Value: $1,116,125.00
Issued Date: August 26, 2011
File Close Date: August 15, 2013

Associated Properties

Address Zone More
6300 HAMMOND BAY ROAD CS1 , CS2 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2013-08-15

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.