BP115414 - 310 Canterbury Crescent - previously 445 Nottingham Drive
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP115414 - 310 Canterbury Crescent - previously 445 Nottingham Drive | |
|---|---|
| Neighbourhood: | Linley Valley |
| Street Address: | 310 Canterbury Crescent - previously 445 Nottingham Drive |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP115414 |
| Date Application Submitted: | July 19, 2010 |
| Application Description: |
Construct a slab on grade two storey single family with an attached double garage Revision Nov 25,2010... Finish Basement completely. Add one bedroom Secondary Suite. Rough ins for Suite Kitchen Laundry and Bathroom done. Suite tub/shower installed.Walkin closet for bedroom. New entry door for suite at back of house and 20 minute rated door to main dwelling. No Kitchen cabinets installed at this time. MLB |
| Application Status: | COMPLETED |
| Permit Value: | $301,735.00 |
| Building Area: |
303.50 M2 3,266.84 ft2 |
| Issued Date: | August 20, 2010 |
| File Close Date: | March 15, 2011 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 310 CANTERBURY CRESCENT | R10 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
|
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2011-03-15 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)