BP114752 - 907 Brookfield Place
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP114752 - 907 Brookfield Place | |
|---|---|
| Neighbourhood: | Harewood |
| Street Address: | 907 Brookfield Place |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP114752 |
| Date Application Submitted: | January 15, 2010 |
| Application Description: |
construct a three storey single family dwelling + legal secondary suite on slab with built-in single garage Revision submitted May 3, 2010; - changing suite kitchen location - adding coat closet - adding 4o3o window on right side AG Revision submitted May 20, 2010: Suite - bathroom fixtures moved Main Flr. - toilet/washbasin moved 2nd Flr. - tub removed, shower added, toilet moved & window added AG |
| Application Status: | COMPLETED |
| Permit Value: | $225,000.00 |
| Building Area: |
199.74 M2 2,149.98 ft2 |
| Builder: | T HASK CONSTRUCTION LTD |
| Issued Date: | February 08, 2010 |
| File Close Date: | February 23, 2011 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 907 BROOKFIELD PLACE | R5 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
|
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
PASSED |
|
STORM CONNECTION
Pipe and Connection must be visible for inspection |
CANCELLED |
|
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
CANCELLED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
WATER CONNECTION
Pipe and Connection must be visable for inspection |
CANCELLED |
|
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2011-02-16 |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2011-02-23 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)