BP114724 - 310 - 60 Commercial
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP114724 - 310 - 60 Commercial | |
|---|---|
| Neighbourhood: | Downtown/Old City |
| Street Address: | 310 - 60 Commercial |
| Type of Application: | Leasehold Improvements |
| File Number: | BP114724 |
| Date Application Submitted: | January 08, 2010 |
| Application Description: |
- Landlord's work- see permit conditions - Coast Capital - 1285 sq. ft. (119m2) - Group D- Landlords works includes the vertical 1 hr. Suite Fire Separation/Fire Resistance Rating. Service penetrations (coring) within the slab . Location and position of mechanical equipment in Parking Garage. Firestopping system for piping transition between the parking garage level (System 15 pipe) and Retail/Museum Level(Cast pipe). Sprinkler changes. x reference BP114727 for Tenant improvements & EW000802 Works in City Street permit. x reference BP110341.VICC, Non-combustible construction, sprinklered with fire alarm. |
| Application Status: | COMPLETED |
| Permit Value: | $20,000.00 |
| Building Area: |
119.00 M2 1,280.90 ft2 |
| Builder: | KOMEN CONTRACTING LTD |
| Issued Date: | January 29, 2010 |
| File Close Date: | July 05, 2010 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 60 COMMERCIAL STREET | DT1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
FAILED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
|
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
|
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
|
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
|
FINAL-OLD
Final Approval as per requirements on plans. |
PASSED
2010-07-05 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.