Application Description: |
Rexall Pharmacy - new 1060m2 single storey, single occupancy retail store, sprinklered with fire alarm system. Plumbing underslab roughed - in. Future permit required to complete and occupy. On-site servicing under BP113769 Building Classification: 3.2.2.62. Group E, one storey <3000m2, sprinklered with fire alarm, combustible ok, 45 min. FS floor assemblies and 45 min. FRR supports. |
Application Status: | COMPLETED |
Permit Value: | $1,200,000.00 |
Builder: | LEDCOR CONSTRUCTION LIMITED |
Issued Date: | April 26, 2010 |
File Close Date: | January 20, 2011 |
Associated Properties
Address | Zone | More |
---|---|---|
1750 DUFFERIN CRESCENT | COR3 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
OCCUPANCY-OLD | CANCELLED |
OCCUPANCY-OLD |
PASSED
2011-01-20 |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2011-01-20 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.