BP114267 - 4725 Rutherford -- Scanned
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP114267 - 4725 Rutherford -- Scanned | |
|---|---|
| Neighbourhood: | Rutherford |
| Street Address: | 4725 Rutherford -- Scanned |
| Type of Application: | Commercial / Multi-Res Alteration |
| File Number: | BP114267 |
| Date Application Submitted: | August 06, 2009 |
| Application Description: |
McDonald's Restaurant of Canada Ltd, . Exterior Facade upgrade; An addition of 1044 sq.ft. of floor area to existing building for a party zone and play area, and an additional 70 sq.ft. of floor area for a new cash area. Changes to the existing building interior , include adding a staff room in the existing basement, renovating the existing dining room , reconfiguration and renovation to the women's and men's washroom, accessible toilet compartments in each and adding a new accessible universal washroom. Providing a 1 hr FRR/FS around the existing janitor's room. Demolition of the existing play area this is replaced by the new addition. Occupant load = 175 persons. Group A, Division 2, Building Classification 3.2.2.28. Building area by code = 5340 sq. ft., One storey with basement, Existing basement = 4051 sq.ft. Unsprinklered, Fire alarm, Combustible construction, floor assemblies = 1 hour FRR/FS. |
| Application Status: | COMPLETED |
| Permit Value: | $250,000.00 |
| Building Area: |
103.40 M2 1,112.99 ft2 |
| Builder: | MIKON CONSTRUCTION LTD |
| Issued Date: | October 19, 2009 |
| File Close Date: | July 14, 2011 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 4725 RUTHERFORD ROAD | CC3 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2011-07-14 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)