| Application Description: |
Murdoch Orthodontics Clinic, 345.6m2 "D" occupancy. Complete and occupy permit includes sprinkler changes, extensive plumbing, universal washroom and 2 additional washrooms, dropped ceilings, interior partitions and millwork. Ensure fire stopping, fire dampers at all penetration of rated fire separations. The 45 min FRR/FS roof-ceiling assembly and the 45 min. FRR/FS demising walls and 1 hr. FRR on the exterior wall are installed under the base building BP112591. Building C: - 6596 Applecross - 1493.46 m2 - Group E/D/Group A2 - Classification 2006BCBC, 3.2.2.62/3.2.2.27, sprinklered, fire alarm, combustible, N & E exterior walls 1 hr. FRR and 45 min. FRR/FS demising walls, 45 min. FRR/ FS roof-ceiling assembly. |
| Application Status: | COMPLETED |
| Permit Value: | $225,000.00 |
| Builder: | MIKON CONSTRUCTION LTD |
| Issued Date: | July 23, 2009 |
| File Close Date: | December 03, 2009 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 6596 APPLECROSS ROAD | CC4 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
CANCELLED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
CANCELLED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
|
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
|
FINAL-OLD
Final Approval as per requirements on plans. |
CANCELLED |
|
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
|
FINAL-OLD
Final Approval as per requirements on plans. |
PASSED
2009-12-03 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)