BP113867 - 6300 Hammond Bay Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP113867 - 6300 Hammond Bay Road | |
|---|---|
| Neighbourhood: | Dover |
| Street Address: | 6300 Hammond Bay Road |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP113867 |
| Date Application Submitted: | December 12, 2008 |
| Application Description: |
RDN Administration Bldg. - 477.7m2 GFA, 2 storey addition and renovation, covered walkway and 35.4m2 covered bike storage & garbage enclosure. INSPECTIONS ONLY RDN Admin. Bldg under this building permit number see BP113597 for main building permit SPRINKLER AS BUILTS ARE IN TRANSIT ADDITION PERMIT FILE |
| Application Status: | COMPLETED |
| Builder: | WINDLEY CONTRACTING LTD |
| Issued Date: | March 05, 2009 |
| File Close Date: | February 15, 2011 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 6300 HAMMOND BAY ROAD | CS1 , CS2 | Property Report |
| 6300 HAMMOND BAY ROAD | Property Report |
Process Steps
| Task | Status |
|---|---|
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
CANCELLED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PARTIAL |
|
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2011-02-15 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)