BP113822 - 1951 Szasz
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP113822 - 1951 Szasz | |
---|---|
Neighbourhood: | Chase River |
Street Address: | 1951 Szasz |
Type of Application: | Garage / Carport Permit |
File Number: | BP113822 |
Date Application Submitted: | March 20, 2009 |
Application Description: |
Physical File Scanned + attached May 29, 2009 db BCLS Certificate of Location attached May 29, 2009 db Construct a new 25'x30' detached garage |
Application Status: | COMPLETED |
Permit Value: | $22,000.00 |
Building Area: |
69.67 M2 749.92 ft2 |
Builder: | G L G CONTRACTING LTD |
Issued Date: | April 20, 2009 |
File Close Date: | March 27, 2009 |
Associated Properties
Address | Zone | More |
---|---|---|
1951 SZASZ DRIVE | R1 | Property Report |
Process Steps
Task | Status |
---|---|
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
COMPLETED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured . For footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
FAILED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
FRAMING
Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
FINAL-OLD
Final Approval as per requested on plans. |
PASSED
2009-05-27 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.