Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP113502 - 490 Eighth | |
---|---|
Neighbourhood: | Harewood |
Street Address: | 490 Eighth |
Type of Application: | Locate Permit |
File Number: | BP113502 |
Date Application Submitted: | November 07, 2008 |
Application Description: | Place a modular home on a full basement with an attached garage and deck |
Application Status: | COMPLETED |
Permit Value: | $47,566.00 |
Building Area: |
3,215.25 M2 34,608.63 ft2 |
Builder: | GORDON'S HOMES SALES LTD |
Issued Date: | November 19, 2008 |
File Close Date: | February 10, 2009 |
Associated Properties
Address | Zone | More |
---|---|---|
490 EIGHTH STREET | R5 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For Perimeter Drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
STORM CONNECTION
Pipe connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe Connection must be visible for inspection. |
PARTIAL |
SANITARY CONNECTION
Pipe Connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe Connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PARTIAL |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
FAILED |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.