BP113501 - 5090 Uplands (parent) 6172/6170 Arlin Place -- Scanned

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP113501 - 5090 Uplands (parent) 6172/6170 Arlin Place -- Scanned
Neighbourhood: Rutherford    
Street Address: 5090 Uplands (parent) 6172/6170 Arlin Place -- Scanned
Type of Application: Commercial / Multi / Industrial
File Number: BP113501
Date Application Submitted: November 05, 2008
Application Description: Strathcona Estates - 35 unit Multi family development - Phase 2 (2 duplexes - strata lots 5/ 6 & 7/8) on Lot 3.

6172/6170 Arlin Place (INSPECTIONS ONLY)

Application Status: COMPLETED
Issued Date: April 15, 2009
File Close Date: October 28, 2009

Associated Properties

Address Zone More
6172 ARLIN PLACE R8 Property Report
6170 ARLIN PLACE R8 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PARTIAL
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2009-10-28

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.