BP113209 - 250 Selby
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP113209 - 250 Selby | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 250 Selby |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP113209 |
Date Application Submitted: | July 28, 2008 |
Application Description: |
27 Unit Apartment Building 3 storey, Group C, residential, combustible low rise, Sprinklered/ fire alarm system. Building classification, Part 9. Building Code area 595m2. Accessible entrance area. 3.8.3 45min FS/FRR floor assemblies 50 STM and exits. 45 min.FS/FRR Public corridor, 45min FS/FRR party walls between suites.50 STM . 20 min labelled suite doors. All doors in fire separations to be self-closing with positive latching mechanisms. Rated roof provided for termination of the partywalls/rated walls. North and South face 45 FRR, combustible. Duct shafts 45 min FS/FRR. Fire stopping in the attic is required. Revision September 26, 2009 change on lower floor level extending the public corridor and new exit door to the exterior. Adding 45 min FRR/FS bike storage room and bathoom in unit M. |
Application Status: | COMPLETED |
Permit Value: | $1,725,333.84 |
Issued Date: | May 13, 2009 |
File Close Date: | February 26, 2010 |
Associated Properties
Address | Zone | More |
---|---|---|
250 SELBY STREET | DT3 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD |
PASSED
2010-02-25 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.