BP112737 - 2575 Bowen Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP112737 - 2575 Bowen Road | |
|---|---|
| Neighbourhood: | Diver Lake |
| Street Address: | 2575 Bowen Road |
| Type of Application: | Commercial / Multi-Res Alteration |
| File Number: | BP112737 |
| Date Application Submitted: | April 10, 2008 |
| Application Description: |
Island Kia Auto Dealership - New 175 sq m. showroom addition joining two existing buildings with new 170 sq m. second storey extending into existing showroom space. Adding 175 sq m. to the main floor and a 170 sq m. second storey. Alternative Solution for exiting exposure and glazing in the fire separation by GHL. New building area 810 sq m. F2 Building Classification is 3.2.2.72 Sprinklered with Fire Alarm, Combustible construction, 45 min FRR/FS for the combustible floor assembly and any combustible floor supports, 2 hr FRR/FS for the wall separating the service garage and the office. Existing was 2 - Part 9 Buildings. 1st building is the Lube Shop - F2 = 88m2. 2nd building is the showroom, offices and the repair garage and parts= 547m2. Group F2 occupancy |
| Application Status: | COMPLETED |
| Permit Value: | $200,000.00 |
| Building Area: |
345.00 M2 3,713.55 ft2 |
| Builder: | ISLAND WEST COAST DEVELOPMENTS |
| Issued Date: | September 12, 2008 |
| File Close Date: | November 24, 2010 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 2575 BOWEN ROAD | COR3 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
|
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2010-11-24 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)