| Application Description: |
Edgewood Treatment Facility. Permit includes on-site civil work on this property and at 2113 Boxwood. Two storey addition to the west side of building. Total floor area added = 592 sq. m New building area including this addition (Phase 2) = 3035 sq. m. Part 3, sprinklered, fire alarm system, 2 storey, combustible construction, Group C, Building Re-Classification: 3.2.2.45., Corridors 1 hr. FRR/FS, doors opening into the corridor to be 45 min FPR with self closing devices, 1 hr. FRR/FS/ 50 STM between sleeping room and other occupancies. Doors of 20 min FPR/self closing, for sleeping rooms only that open into the public corridor. All other doors opening into the public corridor = 45 min. FPR with self closing devices. COVENANT REGISTERED 2008-01-13 |
| Application Status: | COMPLETED |
| Permit Value: | $1,050,000.00 |
| Builder: | TECTONICA MANAGEMENT INC |
| Issued Date: | January 02, 2008 |
| File Close Date: | September 08, 2008 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 2121 BOXWOOD ROAD | CS1 | Property Report |
| 2113 BOXWOOD ROAD | CS1 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
SCHEDULED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
CANCELLED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
CANCELLED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
|
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
| OCCUPANCY-OLD | PARTIAL |
| OCCUPANCY-OLD |
PASSED
2008-09-08 |
|
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)