Date Application Submitted: July 11, 2007
Application Description: Construct a two-storey single family dwelling on slab with an attached single garage. DP000726 has been issued for reduced setbacks

Revision: Add cantilevered deck to rear and bump in to unfinished basement at rear. Aug.26, 2014 - LB
Application Status: COMPLETED
Permit Value: $210,982.04
Building Area: 286.88 M2
3,087.95 ft2
Issued Date: December 18, 2013
File Close Date: December 10, 2014
Expiry Date: December 18, 2015

Associated Properties

Address Zone More
635 RAILWAY AVENUE R5 Property Report

Process Steps

Task Status
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PASSED
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

CANCELLED
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

CANCELLED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

CANCELLED
STORM CONNECTION

Pipe and Connection must be visible for inspection

PASSED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PASSED
WATER CONNECTION

Pipe and Connection must be visable for inspection

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

FAILED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PASSED
OCCUPANCY-OLD

Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish

FAILED
OCCUPANCY-OLD

Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish

PASSED

2014-12-10

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.