BP111665 - 639 Seventh (Parent) 812 Brookfield Phase 2 SL4 VIS6562 -- Scanned
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP111665 - 639 Seventh (Parent) 812 Brookfield Phase 2 SL4 VIS6562 -- Scanned | |
|---|---|
| Neighbourhood: | Harewood |
| Street Address: | 639 Seventh (Parent) 812 Brookfield Phase 2 SL4 VIS6562 -- Scanned |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP111665 |
| Date Application Submitted: | June 15, 2007 |
| Application Description: |
Oakhills Vista - 27 unit multi-family site Phase 2 - 4 Units of a Multi Family Development. Cross reference BP11080 for On-Site Service Permit. Unit 4,5,6,7 are one storey single family dwelling with daylight finished basements and attached garage. 812 Brookfield Dr. (unit 4) 175.1m2GFA + 39.8m2 garage. Inspections tasks under BP111665 816 Brookfield Dr. (unit 5) 175.1m2GFA + 39.8m2 garage. Inspection tasks under BP111701 820 Brookfield Dr. (unit 6) 175.1m2GFA + 39.8m2 garage. Inspection tasks under BP111702 824 Brookfield Dr. (unit 7) 175.1m2GFA + 39.8m2 garage. Inspection tasks under BP111703 Dec. 20, 2007 - 16.5 sq ft bump out added to great room in units 4 & 7. VS Jan. 21, 2008 - 16.5 sq ft bump out added to great room in units 5 & 6. VS |
| Application Status: | COMPLETED |
| Permit Value: | $900,000.00 |
| Builder: | OAKHILLS VISTA DEVELOPMENTS LTD |
| Issued Date: | August 16, 2007 |
| File Close Date: | May 21, 2008 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 812 BROOKFIELD DRIVE | R6 | Property Report |
| 625 SEVENTH STREET | R6 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
| OCCUPANCY-OLD | FAILED |
| OCCUPANCY-OLD |
PASSED
2008-05-21 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)