BP111618 - 4820 Jordan Avenue formally 4904 Goodwin

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP111618 - 4820 Jordan Avenue formally 4904 Goodwin
Neighbourhood: Diver Lake    
Street Address: 4820 Jordan Avenue formally 4904 Goodwin
Type of Application: Commercial / Multi / Industrial
File Number: BP111618
Date Application Submitted: June 04, 2007
Application Description: Slegg - 5018.5m2 one storey warehouse storage / repair garage building, with 165.3m2 enclosed mezzanine < 10% of building area. 2 hr fire separation between repair garage and warehouse. 3/4 hr fire resistance rating for mezzanine floor and supports.

Building Classification 3.2.2.70 Group F-2, sprinklered with fire alarm, combustible construction, one storey < 9600m2, 3/4 hr FRRFS floor assemblies and 3/4 hr FRR for mezzanines and supports.

One sink added in storage area June 18, 08 VS
Physical File Scanned + attached Dec 16, 2008 db
Application Status: COMPLETED
Permit Value: $1,188,000.00
Builder: MALAVIEW DEVELOPMENT LTD
Issued Date: November 21, 2007
File Close Date: August 21, 2008

Associated Properties

Address Zone More
4950 JORDAN AVENUE I2 Property Report
4820 JORDAN AVENUE I2 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

FAILED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PASSED

2008-08-21

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.