BP111553 - 96 Wallace -- Scanned

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP111553 - 96 Wallace -- Scanned
Neighbourhood: Downtown/Old City    
Street Address: 96 Wallace -- Scanned
Type of Application: Commercial / Multi / Industrial
File Number: BP111553
Date Application Submitted: May 17, 2007
Application Description: 305.8m2 three-storey, parking garage with two floors of office above, addition to left side of existing Meyers, Norris, Penny office building; and interior renovations of existing space. Water curtain equivalency by GHL for exiting protection and equivalency for interconnected floors. 1.5hr FRR/FS ceiling/floor assembly & 1.5hr FRR supports for storage garage and 3/4 hr FRR/FS between office floor assemblies, exit stair enclosure and lift on upper floors, 3/4 hr FRR for supports.

374.6m2 existing building + 305.8m2 addition = 680.1m2, Part 3 building, 3.2.2.54 and 3.2.2.77 of 2006 BC Building Code applies, combustible construction, sprinklered with fire alarm system.
Application Status: COMPLETED
Permit Value: $1,040,000.00
Builder: WINDLEY CONTRACTING LTD
Issued Date: August 30, 2007
File Close Date: June 16, 2010

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PASSED
FINAL-OLD

Final approval as per requirements on plans.

FAILED
FINAL-OLD

Final approval as per requirements on plans.

PARTIAL
FINAL-OLD

Final approval as per requirements on plans.

PASSED

2010-06-16

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.