BP111090 - 4224 Gulfview
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP111090 - 4224 Gulfview | |
|---|---|
| Neighbourhood: | Hammond Bay |
| Street Address: | 4224 Gulfview |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP111090 |
| Date Application Submitted: | December 19, 2006 |
| Application Description: |
Construct three-storey single family dwelling with unfinished basement and unfinished sub-basement. Permit includes a three piece plumbing rough-in and 68' of finished area at stairs. Revision submitted June 25, 2007 1) Finish sub- basement (suite). 2) Adding sink, washer and 3-piece bathroom for suite. 3) Adding two windows on sides. 4) Finish basement. 5) Changing from slab to crawlspace for sub-basement. AG |
| Application Status: | COMPLETED |
| Permit Value: | $293,170.88 |
| Building Area: |
136.57 M2 1,470.03 ft2 |
| Issued Date: | March 07, 2007 |
| File Close Date: | October 31, 2007 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 4224 GULFVIEW DRIVE | R10 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PARTIAL |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
FAILED |
|
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
PASSED |
|
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
|
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
CANCELLED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
CANCELLED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
CANCELLED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
CANCELLED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
CANCELLED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
CANCELLED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
|
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2007-10-31 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.