BP111023 - Parent 6000 Uplands - alias 6208 Washington Way - Unit 3 -- Scanned
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP111023 - Parent 6000 Uplands - alias 6208 Washington Way - Unit 3 -- Scanned | |
|---|---|
| Neighbourhood: | Rutherford |
| Street Address: | Parent 6000 Uplands - alias 6208 Washington Way - Unit 3 -- Scanned |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP111023 |
| Date Application Submitted: | October 03, 2006 |
| Application Description: |
Strathcona Estates - Washington Way - Multi family development - 14 single family houses in 3 phases. Phase 1 - This permit is for INSPECTION TASKS ONLY on unit 3. All other information is under BP110764. On and off-site servicing under BP110689. 6208 Washington Way - Unit 3, 180.6m2 gross floor area, 42.9m2 garage Doreen has file May 6, 2009 |
| Application Status: | COMPLETED |
| Builder: | KUNA ENTERPRISES LTD |
| Issued Date: | January 24, 2007 |
| File Close Date: | May 15, 2008 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 6208 WASHINGTON WAY | R8 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
FAILED |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
|
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
|
FINAL-OLD
Final approval as per requirements on plans. |
PARTIAL |
|
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2008-05-15 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)