Type of Application: Commercial / Multi / Industrial
File Number: BP111010
Date Application Submitted: July 19, 2006
Application Description: Vista View 4 building complex - This permit is for INSPECTION TASKS ONLY for Unit D, all other information is held in BP110839. Cross reference BP111425 for foundations.

Unit D1-4954 Vista View, 220.7m2 gross floor area, 49.4m2 garage
Unit D2-4950 Vista View, 206.9m2 gross floor area, 43.5m2 garage

Physical File Scanned + attached Dec 17, 2008 db
Application Status: COMPLETED
Builder: ONE TREE DEVELOPMENTS
Issued Date: July 24, 2007
File Close Date: April 15, 2008

Associated Properties

Address Zone More
4954 VISTA VIEW CRESCENT R6 Property Report
4950 VISTA VIEW CRESCENT R6 Property Report
4960 VISTA VIEW CRESCENT R6 Property Report

Process Steps

Task Status
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
OCCUPANCY-OLD PARTIAL
OCCUPANCY-OLD PASSED

2008-04-15

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.